Certificate ⁦6⁩ — July 2024

Design & build — Al-Khobar branch rehabilitation & extension

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
6
Date
⁦2024-08-09⁩
Hijri
5 Safar 1446 AH
Reference
PAY-2024-003-06

Interim payment certificate no. (⁦6⁩)

For the work of July 2024

Contract number
SCA/2024/003
Etimad reference
2401220043
Contract
Design & build — Al-Khobar branch rehabilitation & extension
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Al-Khobar Branch — Rehabilitation & Extension
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
352,000,000
Current contract value
373,400,000including variations of SAR 21.4M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date33,470,000
2Less: previous certificates(26,360,000)
3Value of work in this certificate7,110,000
4Less: retention (⁦10%⁩)(711,000)
5Less: advance payment recovery (⁦10%⁩)(711,000)
6Less: delay and breach penalties0
7Total deductions(1,422,000)
8Net before VAT5,688,000
9Add: value added tax (15%)853,200
10Net amount payable to the contractor6,541,200

Amount in words: Six million five hundred forty-one thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 3.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation26,138,0004,284,0001,122,0005,406,000⁦21%⁩
Earthworks & foundations67,212,0006,672,0001,762,0008,434,000⁦13%⁩
Concrete & structural works115,754,0008,986,0002,427,00011,413,000⁦10%⁩
Mechanical, electrical & plumbing89,616,0004,399,0001,224,0005,623,000⁦6%⁩
Finishes & external works56,010,0001,760,000499,0002,259,000⁦4%⁩
Testing & commissioning18,670,000259,00076,000335,000⁦2%⁩
Total373,400,00026,360,0007,110,00033,470,000⁦9%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2024-08-09⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-08-11⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2024-08-14⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-08-17⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-08-20⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-08-09⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2024-08-11⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-08-14⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2024-08-17⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-08-20⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2024-10-30⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-07-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

20 August 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-08-20 13:00

17 August 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-08-17 13:00

14 August 2024

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2024-08-14 13:00

11 August 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-08-11 13:00

9 August 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-08-09 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close