Certificate ⁦5⁩ — June 2024

Design & build — Al-Khobar branch rehabilitation & extension

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
5
Date
⁦2024-07-11⁩
Hijri
5 Muharram 1446 AH
Reference
PAY-2024-003-05

Interim payment certificate no. (⁦5⁩)

For the work of June 2024

Contract number
SCA/2024/003
Etimad reference
2401220043
Contract
Design & build — Al-Khobar branch rehabilitation & extension
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Al-Khobar Branch — Rehabilitation & Extension
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
352,000,000
Current contract value
373,400,000including variations of SAR 21.4M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date26,360,000
2Less: previous certificates(19,290,000)
3Value of work in this certificate7,070,000
4Less: retention (⁦10%⁩)(707,000)
5Less: advance payment recovery (⁦10%⁩)(707,000)
6Less: delay and breach penalties0
7Total deductions(1,414,000)
8Net before VAT5,656,000
9Add: value added tax (15%)848,400
10Net amount payable to the contractor6,504,400

Amount in words: Six million five hundred four thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 2.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation26,138,0003,135,0001,122,0004,257,000⁦16%⁩
Earthworks & foundations67,212,0004,884,0001,759,0006,643,000⁦10%⁩
Concrete & structural works115,754,0006,576,0002,413,0008,989,000⁦8%⁩
Mechanical, electrical & plumbing89,616,0003,217,0001,211,0004,428,000⁦5%⁩
Finishes & external works56,010,0001,287,000492,0001,779,000⁦3%⁩
Testing & commissioning18,670,000191,00073,000264,000⁦1%⁩
Total373,400,00019,290,0007,070,00026,360,000⁦7%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2024-07-11⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-07-13⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2024-07-16⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-07-19⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-07-22⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-07-11⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2024-07-13⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-07-16⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2024-07-19⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-07-22⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2024-10-30⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-07-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

22 July 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-07-22 13:00

19 July 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-07-19 13:00

16 July 2024

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2024-07-16 13:00

13 July 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-07-13 13:00

11 July 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-07-11 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close