Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2024-07-11
- Hijri
- 5 Muharram 1446 AH
- Reference
- PAY-2024-003-05
Interim payment certificate no. (5)
For the work of June 2024
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 26,360,000 |
| 2 | Less: previous certificates | (19,290,000) |
| 3 | Value of work in this certificate | 7,070,000 |
| 4 | Less: retention (10%) | (707,000) |
| 5 | Less: advance payment recovery (10%) | (707,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,414,000) |
| 8 | Net before VAT | 5,656,000 |
| 9 | Add: value added tax (15%) | 848,400 |
| 10 | Net amount payable to the contractor | 6,504,400 |
Amount in words: Six million five hundred four thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 2.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 3,135,000 | 1,122,000 | 4,257,000 | 16% |
| Earthworks & foundations | 67,212,000 | 4,884,000 | 1,759,000 | 6,643,000 | 10% |
| Concrete & structural works | 115,754,000 | 6,576,000 | 2,413,000 | 8,989,000 | 8% |
| Mechanical, electrical & plumbing | 89,616,000 | 3,217,000 | 1,211,000 | 4,428,000 | 5% |
| Finishes & external works | 56,010,000 | 1,287,000 | 492,000 | 1,779,000 | 3% |
| Testing & commissioning | 18,670,000 | 191,000 | 73,000 | 264,000 | 1% |
| Total | 373,400,000 | 19,290,000 | 7,070,000 | 26,360,000 | 7% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani