Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 28
- Date
- 2026-05-08
- Hijri
- 21 Dhuʻl-Qiʻdah 1447 AH
- Reference
- PAY-2024-003-28
Interim payment certificate no. (28)
For the work of April 2026
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 247,590,000 |
| 2 | Less: previous certificates | (242,560,000) |
| 3 | Value of work in this certificate | 5,030,000 |
| 4 | Less: retention (10%) | (503,000) |
| 5 | Less: advance payment recovery (10%) | (503,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,006,000) |
| 8 | Net before VAT | 4,024,000 |
| 9 | Add: value added tax (15%) | 603,600 |
| 10 | Net amount payable to the contractor | 4,627,600 |
Amount in words: Four million six hundred twenty-seven thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 24.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 25,768,000 | 370,000 | 26,138,000 | 100% |
| Earthworks & foundations | 67,212,000 | 66,156,000 | 1,056,000 | 67,212,000 | 100% |
| Concrete & structural works | 115,754,000 | 91,553,000 | 1,904,000 | 93,457,000 | 81% |
| Mechanical, electrical & plumbing | 89,616,000 | 40,490,000 | 1,105,000 | 41,595,000 | 46% |
| Finishes & external works | 56,010,000 | 16,203,000 | 509,000 | 16,712,000 | 30% |
| Testing & commissioning | 18,670,000 | 2,390,000 | 86,000 | 2,476,000 | 13% |
| Total | 373,400,000 | 242,560,000 | 5,030,000 | 247,590,000 | 66% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani