Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 13
- Date
- 2025-02-28
- Hijri
- 29 Shaʻban 1446 AH
- Reference
- PAY-2024-003-13
Interim payment certificate no. (13)
For the work of February 2025
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 105,220,000 |
| 2 | Less: previous certificates | (93,080,000) |
| 3 | Value of work in this certificate | 12,140,000 |
| 4 | Less: retention (10%) | (1,214,000) |
| 5 | Less: advance payment recovery (10%) | (1,214,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,428,000) |
| 8 | Net before VAT | 9,712,000 |
| 9 | Add: value added tax (15%) | 1,456,800 |
| 10 | Net amount payable to the contractor | 11,168,800 |
Amount in words: Eleven million one hundred sixty-eight thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 10.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 15,197,000 | 1,797,000 | 16,994,000 | 65% |
| Earthworks & foundations | 67,212,000 | 23,644,000 | 2,871,000 | 26,515,000 | 39% |
| Concrete & structural works | 115,754,000 | 31,722,000 | 4,158,000 | 35,880,000 | 31% |
| Mechanical, electrical & plumbing | 89,616,000 | 15,449,000 | 2,228,000 | 17,677,000 | 20% |
| Finishes & external works | 56,010,000 | 6,162,000 | 940,000 | 7,102,000 | 13% |
| Testing & commissioning | 18,670,000 | 906,000 | 146,000 | 1,052,000 | 6% |
| Total | 373,400,000 | 93,080,000 | 12,140,000 | 105,220,000 | 28% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani