Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 14
- Date
- 2025-03-29
- Hijri
- 29 Ramadan 1446 AH
- Reference
- PAY-2024-003-14
Interim payment certificate no. (14)
For the work of March 2025
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 115,490,000 |
| 2 | Less: previous certificates | (105,220,000) |
| 3 | Value of work in this certificate | 10,270,000 |
| 4 | Less: retention (10%) | (1,027,000) |
| 5 | Less: advance payment recovery (10%) | (1,027,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,054,000) |
| 8 | Net before VAT | 8,216,000 |
| 9 | Add: value added tax (15%) | 1,232,400 |
| 10 | Net amount payable to the contractor | 9,448,400 |
Amount in words: Nine million four hundred forty-eight thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 11.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 17,149,000 | 1,503,000 | 18,652,000 | 71% |
| Earthworks & foundations | 67,212,000 | 26,694,000 | 2,409,000 | 29,103,000 | 43% |
| Concrete & structural works | 115,754,000 | 35,863,000 | 3,519,000 | 39,382,000 | 34% |
| Mechanical, electrical & plumbing | 89,616,000 | 17,498,000 | 1,904,000 | 19,402,000 | 22% |
| Finishes & external works | 56,010,000 | 6,988,000 | 808,000 | 7,796,000 | 14% |
| Testing & commissioning | 18,670,000 | 1,028,000 | 127,000 | 1,155,000 | 6% |
| Total | 373,400,000 | 105,220,000 | 10,270,000 | 115,490,000 | 31% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani