Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 17
- Date
- 2025-06-23
- Hijri
- 27 Dhuʻl-Hijjah 1446 AH
- Reference
- PAY-2024-003-17
Interim payment certificate no. (17)
For the work of June 2025
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 150,310,000 |
| 2 | Less: previous certificates | (139,760,000) |
| 3 | Value of work in this certificate | 10,550,000 |
| 4 | Less: retention (10%) | (1,055,000) |
| 5 | Less: advance payment recovery (10%) | (1,055,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,110,000) |
| 8 | Net before VAT | 8,440,000 |
| 9 | Add: value added tax (15%) | 1,266,000 |
| 10 | Net amount payable to the contractor | 9,706,000 |
Amount in words: Nine million seven hundred six thousand Saudi riyals only
Retention held up to this certificate: SAR 15M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 22,798,000 | 1,477,000 | 24,275,000 | 93% |
| Earthworks & foundations | 67,212,000 | 35,480,000 | 2,398,000 | 37,878,000 | 56% |
| Concrete & structural works | 115,754,000 | 47,633,000 | 3,623,000 | 51,256,000 | 44% |
| Mechanical, electrical & plumbing | 89,616,000 | 23,219,000 | 2,033,000 | 25,252,000 | 28% |
| Finishes & external works | 56,010,000 | 9,267,000 | 879,000 | 10,146,000 | 18% |
| Testing & commissioning | 18,670,000 | 1,363,000 | 140,000 | 1,503,000 | 8% |
| Total | 373,400,000 | 139,760,000 | 10,550,000 | 150,310,000 | 40% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani