Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 18
- Date
- 2025-07-22
- Hijri
- 27 Muharram 1447 AH
- Reference
- PAY-2024-003-18
Interim payment certificate no. (18)
For the work of July 2025
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 162,900,000 |
| 2 | Less: previous certificates | (150,310,000) |
| 3 | Value of work in this certificate | 12,590,000 |
| 4 | Less: retention (10%) | (1,259,000) |
| 5 | Less: advance payment recovery (10%) | (1,259,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,518,000) |
| 8 | Net before VAT | 10,072,000 |
| 9 | Add: value added tax (15%) | 1,510,800 |
| 10 | Net amount payable to the contractor | 11,582,800 |
Amount in words: Eleven million five hundred eighty-two thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 16.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 24,419,000 | 1,719,000 | 26,138,000 | 100% |
| Earthworks & foundations | 67,212,000 | 38,385,000 | 2,836,000 | 41,221,000 | 61% |
| Concrete & structural works | 115,754,000 | 51,222,000 | 4,327,000 | 55,549,000 | 48% |
| Mechanical, electrical & plumbing | 89,616,000 | 24,903,000 | 2,464,000 | 27,367,000 | 31% |
| Finishes & external works | 56,010,000 | 9,923,000 | 1,073,000 | 10,996,000 | 20% |
| Testing & commissioning | 18,670,000 | 1,458,000 | 171,000 | 1,629,000 | 9% |
| Total | 373,400,000 | 150,310,000 | 12,590,000 | 162,900,000 | 44% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani