Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 25
- Date
- 2026-02-10
- Hijri
- 22 Shaʻban 1447 AH
- Reference
- PAY-2024-003-25
Interim payment certificate no. (25)
For the work of January 2026
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 229,080,000 |
| 2 | Less: previous certificates | (222,050,000) |
| 3 | Value of work in this certificate | 7,030,000 |
| 4 | Less: retention (10%) | (703,000) |
| 5 | Less: advance payment recovery (10%) | (703,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,406,000) |
| 8 | Net before VAT | 5,624,000 |
| 9 | Add: value added tax (15%) | 843,600 |
| 10 | Net amount payable to the contractor | 6,467,600 |
Amount in words: Six million four hundred sixty-seven thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 22.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 25,543,000 | 595,000 | 26,138,000 | 100% |
| Earthworks & foundations | 67,212,000 | 65,545,000 | 1,667,000 | 67,212,000 | 100% |
| Concrete & structural works | 115,754,000 | 77,029,000 | 2,462,000 | 79,491,000 | 69% |
| Mechanical, electrical & plumbing | 89,616,000 | 36,977,000 | 1,508,000 | 38,485,000 | 43% |
| Finishes & external works | 56,010,000 | 14,778,000 | 685,000 | 15,463,000 | 28% |
| Testing & commissioning | 18,670,000 | 2,178,000 | 113,000 | 2,291,000 | 12% |
| Total | 373,400,000 | 222,050,000 | 7,030,000 | 229,080,000 | 61% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani