Certificate ⁦11⁩ — January 2026

Jeddah branch & qualification centre — civil & ground-improvement works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
11
Date
⁦2026-02-12⁩
Hijri
24 Shaʻban 1447 AH
Reference
PAY-2024-019-11

Interim payment certificate no. (⁦11⁩)

For the work of January 2026

Contract number
SCA/2024/019
Etimad reference
2402340251
Contract
Jeddah branch & qualification centre — civil & ground-improvement works
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
Jeddah Branch & Qualification Centre
Contract period
⁦2024-10-01⁩ — ⁦2027-03-31⁩
Original contract value
228,000,000
Current contract value
237,600,000including variations of SAR 9.6M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date73,400,000
2Less: previous certificates(66,830,000)
3Value of work in this certificate6,570,000
4Less: retention (⁦10%⁩)(657,000)
5Less: advance payment recovery (⁦10%⁩)(657,000)
6Less: delay and breach penalties0
7Total deductions(1,314,000)
8Net before VAT5,256,000
9Add: value added tax (15%)788,400
10Net amount payable to the contractor6,044,400

Amount in words: Six million forty-four thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 7.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation16,632,00010,892,000962,00011,854,000⁦71%⁩
Earthworks & foundations42,768,00016,955,0001,542,00018,497,000⁦43%⁩
Concrete & structural works73,656,00022,778,0002,251,00025,029,000⁦34%⁩
Mechanical, electrical & plumbing57,024,00011,113,0001,218,00012,331,000⁦22%⁩
Finishes & external works35,640,0004,438,000517,0004,955,000⁦14%⁩
Testing & commissioning11,880,000654,00080,000734,000⁦6%⁩
Total237,600,00066,830,0006,570,00073,400,000⁦31%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-02-12⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-14⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-02-17⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-02-20⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-02-23⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-12⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-02-14⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-02-17⁩

    Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres

    Took 3 days

  4. Payment order prepared⁦2026-02-20⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-23⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-14⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

23 February 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-02-23 13:00

20 February 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-02-20 13:00

17 February 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-02-17 13:00

14 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-02-14 13:00

12 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-12 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close