Interim payment certificate no. (13)
For the work of April 2026
- Contract number
- SCA/2024/019
- Etimad reference
- 2402340251
- Contract
- Jeddah branch & qualification centre — civil & ground-improvement works
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Jeddah Branch & Qualification Centre
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- 228,000,000
- Current contract value
- 237,600,000including variations of SAR 9.6M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 85,410,000 |
| 2 | Less: previous certificates | (79,840,000) |
| 3 | Value of work in this certificate | 5,570,000 |
| 4 | Less: retention (10%) | (557,000) |
| 5 | Less: advance payment recovery (10%) | (557,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,114,000) |
| 8 | Net before VAT | 4,456,000 |
| 9 | Add: value added tax (15%) | 668,400 |
| 10 | Net amount payable to the contractor | 5,124,400 |
Amount in words: Five million one hundred twenty-four thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 8.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 16,632,000 | 12,997,000 | 797,000 | 13,794,000 | 83% |
| Earthworks & foundations | 42,768,000 | 20,237,000 | 1,286,000 | 21,523,000 | 50% |
| Concrete & structural works | 73,656,000 | 27,214,000 | 1,911,000 | 29,125,000 | 40% |
| Mechanical, electrical & plumbing | 57,024,000 | 13,295,000 | 1,054,000 | 14,349,000 | 25% |
| Finishes & external works | 35,640,000 | 5,313,000 | 452,000 | 5,765,000 | 16% |
| Testing & commissioning | 11,880,000 | 784,000 | 70,000 | 854,000 | 7% |
| Total | 237,600,000 | 79,840,000 | 5,570,000 | 85,410,000 | 36% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani