Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 16
- Date
- 2026-09-14
- Hijri
- 3 Rabiʻ II 1448 AH
- Reference
- PAY-2026-010
Interim payment certificate no. (16)
For the work of August 2026
- Contract number
- SCA/2024/019
- Etimad reference
- 2402340251
- Contract
- Jeddah branch & qualification centre — civil & ground-improvement works
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Jeddah Branch & Qualification Centre
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- 228,000,000
- Current contract value
- 237,600,000including variations of SAR 9.6M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 98,400,000 |
| 2 | Less: previous certificates | (92,100,000) |
| 3 | Value of work in this certificate | 6,300,000 |
| 4 | Less: retention (10%) | (630,000) |
| 5 | Less: advance payment recovery (10%) | (630,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,260,000) |
| 8 | Net before VAT | 5,040,000 |
| 9 | Add: value added tax (15%) | 756,000 |
| 10 | Net amount payable to the contractor | 5,796,000 |
Amount in words: Five million seven hundred ninety-six thousand Saudi riyals only
Retention held up to this certificate: SAR 9.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 16,632,000 | 15,015,000 | 877,000 | 15,892,000 | 96% |
| Earthworks & foundations | 42,768,000 | 23,371,000 | 1,426,000 | 24,797,000 | 58% |
| Concrete & structural works | 73,656,000 | 31,390,000 | 2,164,000 | 33,554,000 | 46% |
| Mechanical, electrical & plumbing | 57,024,000 | 15,311,000 | 1,220,000 | 16,531,000 | 29% |
| Finishes & external works | 35,640,000 | 6,113,000 | 529,000 | 6,642,000 | 19% |
| Testing & commissioning | 11,880,000 | 900,000 | 84,000 | 984,000 | 8% |
| Total | 237,600,000 | 92,100,000 | 6,300,000 | 98,400,000 | 41% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani