SCA/2024/019
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 22.5M — if approved the value becomes SAR 260.1M
41% of the current value paid
Paid
98.4Mof a current value of SAR 237.6M
Value of each certificate
The last 14 — gross and net
Approved: 16
Count: 17 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 17September 2026 | 2026-10-14 | 5.9M | 590K | 590K | 708K | 5.4M | Submitted | |
| Certificate 16August 2026 | 2026-09-14 | 6.3M | 630K | 630K | 756K | 5.8M | Approved | |
| Certificate 15July 2026 | 2026-08-13 | 2.9M | 288K | 288K | 345.6K | 2.6M | Approved | |
| Certificate 14June 2026 | 2026-06-29 | 3.8M | 381K | 381K | 457.2K | 3.5M | Approved | |
| Certificate 13April 2026 | 2026-05-14 | 5.6M | 557K | 557K | 668.4K | 5.1M | Approved | |
| Certificate 12March 2026 | 2026-03-30 | 6.4M | 644K | 644K | 772.8K | 5.9M | Approved | |
| Certificate 11January 2026 | 2026-02-12 | 6.6M | 657K | 657K | 788.4K | 6M | Approved | |
| Certificate 10December 2025 | 2025-12-29 | 8.7M | 867K | 867K | 1M | 8M | Approved | |
| Certificate 9October 2025 | 2025-11-13 | 7.9M | 786K | 786K | 943.2K | 7.2M | Approved | |
| Certificate 8September 2025 | 2025-09-29 | 8M | 804K | 804K | 964.8K | 7.4M | Approved | |
| Certificate 7July 2025 | 2025-08-15 | 9.1M | 912K | 912K | 1.1M | 8.4M | Approved | |
| Certificate 6June 2025 | 2025-06-30 | 7.1M | 711K | 711K | 853.2K | 6.5M | Approved | |
| Certificate 5April 2025 | 2025-05-16 | 7.4M | 737K | 737K | 884.4K | 6.8M | Approved | |
| Certificate 4March 2025 | 2025-03-31 | 6.7M | 670K | 670K | 804K | 6.2M | Approved | |
| Certificate 3January 2025 | 2025-02-14 | 4.8M | 482K | 482K | 578.4K | 4.4M | Approved | |
| Certificate 2December 2024 | 2024-12-30 | 4.3M | 431K | 431K | 517.2K | 4M | Approved | |
| Certificate 1October 2024 | 2024-11-15 | 2.8M | 283K | 283K | 339.6K | 2.6M | Approved |