Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2025-05-16
- Hijri
- 18 Dhuʻl-Qiʻdah 1446 AH
- Reference
- PAY-2024-019-05
Interim payment certificate no. (5)
For the work of April 2025
- Contract number
- SCA/2024/019
- Etimad reference
- 2402340251
- Contract
- Jeddah branch & qualification centre — civil & ground-improvement works
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Jeddah Branch & Qualification Centre
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- 228,000,000
- Current contract value
- 237,600,000including variations of SAR 9.6M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 26,030,000 |
| 2 | Less: previous certificates | (18,660,000) |
| 3 | Value of work in this certificate | 7,370,000 |
| 4 | Less: retention (10%) | (737,000) |
| 5 | Less: advance payment recovery (10%) | (737,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,474,000) |
| 8 | Net before VAT | 5,896,000 |
| 9 | Add: value added tax (15%) | 884,400 |
| 10 | Net amount payable to the contractor | 6,780,400 |
Amount in words: Six million seven hundred eighty thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 2.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 16,632,000 | 3,047,000 | 1,157,000 | 4,204,000 | 25% |
| Earthworks & foundations | 42,768,000 | 4,741,000 | 1,819,000 | 6,560,000 | 15% |
| Concrete & structural works | 73,656,000 | 6,359,000 | 2,517,000 | 8,876,000 | 12% |
| Mechanical, electrical & plumbing | 57,024,000 | 3,096,000 | 1,277,000 | 4,373,000 | 8% |
| Finishes & external works | 35,640,000 | 1,235,000 | 522,000 | 1,757,000 | 5% |
| Testing & commissioning | 11,880,000 | 182,000 | 78,000 | 260,000 | 2% |
| Total | 237,600,000 | 18,660,000 | 7,370,000 | 26,030,000 | 11% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani