Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2025-06-30
- Hijri
- 5 Muharram 1447 AH
- Reference
- PAY-2024-019-06
Interim payment certificate no. (6)
For the work of June 2025
- Contract number
- SCA/2024/019
- Etimad reference
- 2402340251
- Contract
- Jeddah branch & qualification centre — civil & ground-improvement works
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Jeddah Branch & Qualification Centre
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- 228,000,000
- Current contract value
- 237,600,000including variations of SAR 9.6M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 33,140,000 |
| 2 | Less: previous certificates | (26,030,000) |
| 3 | Value of work in this certificate | 7,110,000 |
| 4 | Less: retention (10%) | (711,000) |
| 5 | Less: advance payment recovery (10%) | (711,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,422,000) |
| 8 | Net before VAT | 5,688,000 |
| 9 | Add: value added tax (15%) | 853,200 |
| 10 | Net amount payable to the contractor | 6,541,200 |
Amount in words: Six million five hundred forty-one thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 3.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 16,632,000 | 4,246,000 | 1,106,000 | 5,352,000 | 32% |
| Earthworks & foundations | 42,768,000 | 6,608,000 | 1,743,000 | 8,351,000 | 20% |
| Concrete & structural works | 73,656,000 | 8,872,000 | 2,429,000 | 11,301,000 | 15% |
| Mechanical, electrical & plumbing | 57,024,000 | 4,325,000 | 1,243,000 | 5,568,000 | 10% |
| Finishes & external works | 35,640,000 | 1,726,000 | 511,000 | 2,237,000 | 6% |
| Testing & commissioning | 11,880,000 | 253,000 | 78,000 | 331,000 | 3% |
| Total | 237,600,000 | 26,030,000 | 7,110,000 | 33,140,000 | 14% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani