Guarding-contract savings after moving to central monitoring

Off track

Cost saving · Smart Test-hall Proctoring & Access Control

Baseline

0 SAR M

At go-live, ⁦2026-05-01⁩

Latest reading

0.70 SAR M

3 mo reading

Target after 24 months

7.20 SAR M

On ⁦2028-05-01⁩

Target trajectory vs realised

Monthly readings up to the last measurement, then the forecast if performance keeps its current ratio to plan.

Target trajectory vs realised
  • Realised
  • Target trajectory
  • Forecast
Target trajectory vs realised
PeriodRealisedTarget trajectory
2026-050 SAR M0 SAR M
2026-060.37 SAR M0.30 SAR M
2026-070.56 SAR M0.60 SAR M
2026-080.70 SAR M0.90 SAR M
2026-09 (Forecast)0.93 SAR M1.20 SAR M
2026-10 (Forecast)1.17 SAR M1.50 SAR M
2026-11 (Forecast)1.40 SAR M1.80 SAR M
2026-12 (Forecast)1.63 SAR M2.10 SAR M
2027-01 (Forecast)1.87 SAR M2.40 SAR M
2027-02 (Forecast)2.10 SAR M2.70 SAR M
2027-03 (Forecast)2.33 SAR M3 SAR M
2027-04 (Forecast)2.57 SAR M3.30 SAR M
2027-05 (Forecast)2.80 SAR M3.60 SAR M
2027-06 (Forecast)3.03 SAR M3.90 SAR M
2027-07 (Forecast)3.27 SAR M4.20 SAR M
2027-08 (Forecast)3.50 SAR M4.50 SAR M
2027-09 (Forecast)3.73 SAR M4.80 SAR M
2027-10 (Forecast)3.97 SAR M5.10 SAR M
2027-11 (Forecast)4.20 SAR M5.40 SAR M
2027-12 (Forecast)4.43 SAR M5.70 SAR M
2028-01 (Forecast)4.67 SAR M6 SAR M
2028-02 (Forecast)4.90 SAR M6.30 SAR M
2028-03 (Forecast)5.13 SAR M6.60 SAR M
2028-04 (Forecast)5.37 SAR M6.90 SAR M
2028-05 (Forecast)5.60 SAR M7.20 SAR M

Measurement schedule

Counted from go-live on ⁦2026-05-01⁩ · data read Monthly

  1. 3

    After 3 months

    2026-08-0118 Safar 1448 AH·Expected 0.90 SAR M·Actual 0.70 SAR M

    to plan⁦78%⁩
  2. 6

    After 6 months

    2026-11-0121 Jumada I 1448 AH·Expected 1.80 SAR M

    In 4 days2026-11-0121 Jumada I 1448 AH
  3. 12

    After 12 months

    2027-05-0124 Dhuʻl-Qiʻdah 1448 AH·Expected 3.60 SAR M

    In 185 days2027-05-0124 Dhuʻl-Qiʻdah 1448 AH
  4. 24

    After 24 months

    2028-05-016 Dhuʻl-Hijjah 1449 AH·Expected 7.20 SAR M

    In 551 days2028-05-016 Dhuʻl-Hijjah 1449 AH

Evidence

3 files backing the readings

  • Measurement data extract — 3 mo

    2026-08-01 · Eng. Waleed O. Al-Juhani · ⁦117⁩ KB

  • Benefit measurement report — 3 mo

    2026-08-01 · Eng. Waleed O. Al-Juhani · ⁦923⁩ KB

  • Approved benefit profile — BEN-019

    2026-03-01 · Eng. Waleed O. Al-Juhani · ⁦412⁩ KB

Corrective actions

What is being done to bring the benefit back to plan

No actions yet — add a plan to bring the benefit back on track.

Activity

1 August 2026

  1. Milestone: Eng. Waleed O. Al-Juhani recorded the ⁦3⁩ mo reading: ⁦0.70⁩ SAR M

    2026-08-01 10:30

1 March 2026

  1. Approval: Eng. Waleed O. Al-Juhani approved the benefit profile and its baseline

    2026-03-01 09:00