Certificate ⁦18⁩ — January 2026

SCA Academy campus, Riyadh — civil & MEP works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
18
Date
⁦2026-02-01⁩
Hijri
13 Shaʻban 1447 AH
Reference
PAY-2024-006-18

Interim payment certificate no. (⁦18⁩)

For the work of January 2026

Contract number
SCA/2024/006
Etimad reference
2401430082
Contract
SCA Academy campus, Riyadh — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
SCA Academy Campus, Riyadh
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
560,000,000
Current contract value
584,000,000including variations of SAR 24M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date307,260,000
2Less: previous certificates(289,270,000)
3Value of work in this certificate17,990,000
4Less: retention (⁦10%⁩)(1,799,000)
5Less: advance payment recovery (⁦10%⁩)(1,799,000)
6Less: delay and breach penalties0
7Total deductions(3,598,000)
8Net before VAT14,392,000
9Add: value added tax (15%)2,158,800
10Net amount payable to the contractor16,550,800

Amount in words: Sixteen million five hundred fifty thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 30.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation40,880,00038,963,0001,917,00040,880,000⁦100%⁩
Earthworks & foundations105,120,00081,867,0004,304,00086,171,000⁦82%⁩
Concrete & structural works181,040,00098,586,0006,190,000104,776,000⁦58%⁩
Mechanical, electrical & plumbing140,160,00047,942,0003,678,00051,620,000⁦37%⁩
Finishes & external works87,600,00019,104,0001,636,00020,740,000⁦24%⁩
Testing & commissioning29,200,0002,808,000265,0003,073,000⁦11%⁩
Total584,000,000289,270,00017,990,000307,260,000⁦53%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-02-01⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-03⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2026-02-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-02-09⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-02-12⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-01⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-02-03⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-02-06⁩

    Eng. Shahad M. Al-Malki · Director, Academy Facilities

    Took 3 days

  4. Payment order prepared⁦2026-02-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-12⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-05-18⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Dr. Abdullah S. Al-Qahtani

Certificate history

12 February 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-02-12 13:00

9 February 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-02-09 13:00

6 February 2026

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2026-02-06 13:00

3 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”