Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 23
- Date
- 2026-08-12
- Hijri
- 29 Safar 1448 AH
- Reference
- PAY-2024-006-23
Interim payment certificate no. (23)
For the work of July 2026
- Contract number
- SCA/2024/006
- Etimad reference
- 2401430082
- Contract
- SCA Academy campus, Riyadh — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- SCA Academy Campus, Riyadh
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 360,400,000 |
| 2 | Less: previous certificates | (353,720,000) |
| 3 | Value of work in this certificate | 6,680,000 |
| 4 | Less: retention (10%) | (668,000) |
| 5 | Less: advance payment recovery (10%) | (668,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,336,000) |
| 8 | Net before VAT | 5,344,000 |
| 9 | Add: value added tax (15%) | 801,600 |
| 10 | Net amount payable to the contractor | 6,145,600 |
Amount in words: Six million one hundred forty-five thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 36M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 40,321,000 | 559,000 | 40,880,000 | 100% |
| Earthworks & foundations | 105,120,000 | 103,550,000 | 1,570,000 | 105,120,000 | 100% |
| Concrete & structural works | 181,040,000 | 123,568,000 | 2,354,000 | 125,922,000 | 70% |
| Mechanical, electrical & plumbing | 140,160,000 | 59,112,000 | 1,435,000 | 60,547,000 | 43% |
| Finishes & external works | 87,600,000 | 23,674,000 | 653,000 | 24,327,000 | 28% |
| Testing & commissioning | 29,200,000 | 3,495,000 | 109,000 | 3,604,000 | 12% |
| Total | 584,000,000 | 353,720,000 | 6,680,000 | 360,400,000 | 62% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani