AI insight
An escalated contract needs a decision
Open claims: 2; pending variations worth SAR 18.6M. A settlement session with the contractor is advised before deciding the next certificate.
Confidence84%
SCA/2024/006
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 18.6M — if approved the value becomes SAR 602.6M
64% of the current value paid
Paid
371.5Mof a current value of SAR 584M
AI insight
Open claims: 2; pending variations worth SAR 18.6M. A settlement session with the contractor is advised before deciding the next certificate.
Value of each certificate
The last 14 — gross and net
Approved: 24
Count: 25 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 25September 2026 | 2026-10-13 | 9.8M | 980K | 2.2M | 988.5K | 7.6M | Escalated | |
| Certificate 24August 2026 | 2026-09-13 | 11.1M | 1.1M | 1.1M | 1.3M | 10.2M | Approved | |
| Certificate 23July 2026 | 2026-08-12 | 6.7M | 668K | 668K | 801.6K | 6.1M | Approved | |
| Certificate 22June 2026 | 2026-07-05 | 8.3M | 834K | 834K | 1M | 7.7M | Approved | |
| Certificate 21May 2026 | 2026-05-27 | 11.6M | 1.2M | 1.2M | 1.4M | 10.7M | Approved | |
| Certificate 20March 2026 | 2026-04-19 | 12.6M | 1.3M | 1.3M | 1.5M | 11.5M | Approved | |
| Certificate 19February 2026 | 2026-03-11 | 14M | 1.4M | 1.4M | 1.7M | 12.9M | Approved | |
| Certificate 18January 2026 | 2026-02-01 | 18M | 1.8M | 1.8M | 2.2M | 16.6M | Approved | |
| Certificate 17December 2025 | 2025-12-24 | 16.4M | 1.6M | 1.6M | 2M | 15.1M | Approved | |
| Certificate 16October 2025 | 2025-11-16 | 19.2M | 1.9M | 1.9M | 2.3M | 17.7M | Approved | |
| Certificate 15September 2025 | 2025-10-08 | 21.7M | 2.2M | 2.2M | 2.6M | 19.9M | Approved | |
| Certificate 14August 2025 | 2025-08-31 | 18.6M | 1.9M | 1.9M | 2.2M | 17.1M | Approved | |
| Certificate 13July 2025 | 2025-07-23 | 22.8M | 2.3M | 2.3M | 2.7M | 20.9M | Approved | |
| Certificate 12May 2025 | 2025-06-15 | 21.8M | 2.2M | 2.2M | 2.6M | 20.1M | Approved | |
| Certificate 11April 2025 | 2025-05-07 | 19.3M | 1.9M | 1.9M | 2.3M | 17.7M | Approved | |
| Certificate 10March 2025 | 2025-03-30 | 23.1M | 2.3M | 2.3M | 2.8M | 21.2M | Approved | |
| Certificate 9January 2025 | 2025-02-19 | 19.2M | 1.9M | 1.9M | 2.3M | 17.6M | Approved | |
| Certificate 8December 2024 | 2025-01-12 | 18.3M | 1.8M | 1.8M | 2.2M | 16.9M | Approved | |
| Certificate 7November 2024 | 2024-12-04 | 19.6M | 2M | 2M | 2.4M | 18M | Approved | |
| Certificate 6October 2024 | 2024-10-27 | 15M | 1.5M | 1.5M | 1.8M | 13.8M | Approved | |
| Certificate 5August 2024 | 2024-09-18 | 15M | 1.5M | 1.5M | 1.8M | 13.8M | Approved | |
| Certificate 4July 2024 | 2024-08-11 | 13.5M | 1.3M | 1.3M | 1.6M | 12.4M | Approved | |
| Certificate 3June 2024 | 2024-07-03 | 10.1M | 1M | 1M | 1.2M | 9.3M | Approved | |
| Certificate 2May 2024 | 2024-05-26 | 9.2M | 915K | 915K | 1.1M | 8.4M | Approved | |
| Certificate 1March 2024 | 2024-04-17 | 6.6M | 664K | 664K | 796.8K | 6.1M | Approved |