Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦22⁩ — June 2026

SCA Academy campus, Riyadh — civil & MEP works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
22
Date
⁦2026-07-05⁩
Hijri
20 Muharram 1448 AH
Reference
PAY-2024-006-22

Interim payment certificate no. (⁦22⁩)

For the work of June 2026

Contract number
SCA/2024/006
Etimad reference
2401430082
Contract
SCA Academy campus, Riyadh — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
SCA Academy Campus, Riyadh
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
560,000,000
Current contract value
584,000,000including variations of SAR 24M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date353,720,000
2Less: previous certificates(345,380,000)
3Value of work in this certificate8,340,000
4Less: retention (⁦10%⁩)(834,000)
5Less: advance payment recovery (⁦10%⁩)(834,000)
6Less: delay and breach penalties0
7Total deductions(1,668,000)
8Net before VAT6,672,000
9Add: value added tax (15%)1,000,800
10Net amount payable to the contractor7,672,800

Amount in words: Seven million six hundred seventy-two thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 35.4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation40,880,00040,159,000721,00040,880,000⁦100%⁩
Earthworks & foundations105,120,000103,104,0002,016,000105,120,000⁦100%⁩
Concrete & structural works181,040,000118,003,0002,879,000120,882,000⁦67%⁩
Mechanical, electrical & plumbing140,160,00057,643,0001,782,00059,425,000⁦42%⁩
Finishes & external works87,600,00023,068,000808,00023,876,000⁦27%⁩
Testing & commissioning29,200,0003,403,000134,0003,537,000⁦12%⁩
Total584,000,000345,380,0008,340,000353,720,000⁦61%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-07-05⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-07⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2026-07-10⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-13⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-16⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-05⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-07-07⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-07-10⁩

    Eng. Shahad M. Al-Malki · Director, Academy Facilities

    Took 3 days

  4. Payment order prepared⁦2026-07-13⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-16⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-05-18⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Dr. Abdullah S. Al-Qahtani

Certificate history

16 July 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-16 13:00

13 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-13 13:00

10 July 2026

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2026-07-10 13:00

7 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-07 13:00

5 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-05 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close