Interim payment certificate no. (20)
For the work of March 2026
- Contract number
- SCA/2024/006
- Etimad reference
- 2401430082
- Contract
- SCA Academy campus, Riyadh — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- SCA Academy Campus, Riyadh
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 333,790,000 |
| 2 | Less: previous certificates | (321,240,000) |
| 3 | Value of work in this certificate | 12,550,000 |
| 4 | Less: retention (10%) | (1,255,000) |
| 5 | Less: advance payment recovery (10%) | (1,255,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,510,000) |
| 8 | Net before VAT | 10,040,000 |
| 9 | Add: value added tax (15%) | 1,506,000 |
| 10 | Net amount payable to the contractor | 11,546,000 |
Amount in words: Eleven million five hundred forty-six thousand Saudi riyals only
Retention held up to this certificate: SAR 33.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 39,693,000 | 1,187,000 | 40,880,000 | 100% |
| Earthworks & foundations | 105,120,000 | 94,105,000 | 3,037,000 | 97,142,000 | 92% |
| Concrete & structural works | 181,040,000 | 109,501,000 | 4,321,000 | 113,822,000 | 63% |
| Mechanical, electrical & plumbing | 140,160,000 | 53,447,000 | 2,630,000 | 56,077,000 | 40% |
| Finishes & external works | 87,600,000 | 21,349,000 | 1,182,000 | 22,531,000 | 26% |
| Testing & commissioning | 29,200,000 | 3,145,000 | 193,000 | 3,338,000 | 11% |
| Total | 584,000,000 | 321,240,000 | 12,550,000 | 333,790,000 | 57% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani