Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦7⁩ — March 2025

Electronic model contracts platform development

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
7
Date
⁦2025-04-03⁩
Hijri
5 Shawwal 1446 AH
Reference
PAY-2024-009-07

Interim payment certificate no. (⁦7⁩)

For the work of March 2025

Contract number
SCA/2024/009
Etimad reference
2401640121
Contract
Electronic model contracts platform development
Contractor
Digital Platforms Solutions Co.
Contractor VAT number
310105738640003
Project
Electronic Model Contracts
Contract period
⁦2024-05-05⁩ — ⁦2025-07-31⁩
Original contract value
6,900,000
Current contract value
6,900,000
Linked milestone
Go-live · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date5,280,000
2Less: previous certificates(4,330,000)
3Value of work in this certificate950,000
4Less: retention (⁦5%⁩)(47,500)
5Less: advance payment recovery (⁦10%⁩)(95,000)
6Less: delay and breach penalties0
7Total deductions(142,500)
8Net before VAT807,500
9Add: value added tax (15%)121,125
10Net amount payable to the contractor928,625

Amount in words: Nine hundred twenty-eight thousand six hundred twenty-five Saudi riyals only

Retention held up to this certificate: SAR 264K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design1,035,000923,000112,0001,035,000⁦100%⁩
Licences & platform1,380,0001,181,000199,0001,380,000⁦100%⁩
Build & configuration2,070,0001,364,000339,0001,703,000⁦82%⁩
Systems integration1,035,000485,000149,000634,000⁦61%⁩
Testing & acceptance690,000231,00086,000317,000⁦46%⁩
Training & run690,000146,00065,000211,000⁦31%⁩
Total6,900,0004,330,000950,0005,280,000⁦77%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Rayan M. Al-Shehri

Al-Shehri⁦2025-04-03⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2025-04-05⁩

Project manager

Karim Haddad

Haddad⁦2025-04-08⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-04-11⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2025-04-14⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-04-03⁩

    Rayan M. Al-Shehri

  2. Engineer verifies quantities⁦2025-04-05⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2025-04-08⁩

    Karim Haddad · Senior Digital Delivery Consultant — PMO

    Took 3 days

  4. Payment order prepared⁦2025-04-11⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-04-14⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneGo-liveDone · ⁦2025-05-11⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone approved ⁦2025-04-30⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentKarim Haddad → Munirah A. Al-Khalidi

Certificate history

14 April 2025

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2025-04-14 13:00

11 April 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-04-11 13:00

8 April 2025

  1. Approval: Karim Haddad signed “Project manager certifies”

    2025-04-08 13:00

5 April 2025

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2025-04-05 13:00

3 April 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-04-03 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close