Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦14⁩ — March 2026

Supervision — Qassim qualification centre

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
14
Date
⁦2026-04-05⁩
Hijri
17 Shawwal 1447 AH
Reference
PAY-2024-018-14

Interim payment certificate no. (⁦14⁩)

For the work of March 2026

Contract number
SCA/2024/018
Etimad reference
2402270238
Contract
Supervision — Qassim qualification centre
Contractor
Bait Al-Khebra Engineering Consultants
Contractor VAT number
310101872060003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-08-31⁩
Original contract value
9,400,000
Current contract value
9,400,000
Linked milestone
Supervision to substantial completion · MS-G5 Final handover

Certificate summary (SAR)

1Total value of work completed to date3,980,000
2Less: previous certificates(3,730,000)
3Value of work in this certificate250,000
4Less: retention (⁦5%⁩)(12,500)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(12,500)
8Net before VAT237,500
9Add: value added tax (15%)35,625
10Net amount payable to the contractor273,125

Amount in words: Two hundred seventy-three thousand one hundred twenty-five Saudi riyals only

Retention held up to this certificate: SAR 199K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff5,828,0002,328,000156,0002,484,000⁦43%⁩
Visiting specialists1,692,000671,00045,000716,000⁦42%⁩
Laboratory & testing1,128,000402,00028,000430,000⁦38%⁩
Reporting & technical office752,000329,00021,000350,000⁦47%⁩
Total9,400,0003,730,000250,0003,980,000⁦42%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Nader F. Al-Asiri

Al-Asiri⁦2026-04-05⁩

Supervising engineer

Haifa S. Al-Ruwaili

Al-Ruwaili⁦2026-04-07⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-04-10⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-04-13⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2026-04-16⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-05⁩

    Eng. Nader F. Al-Asiri

  2. Engineer verifies quantities⁦2026-04-07⁩

    Haifa S. Al-Ruwaili · Senior Financial Analyst

    Took 2 days

  3. Project manager certifies⁦2026-04-10⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-04-13⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-04-16⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision to substantial completionIn progress · ⁦2027-03-11⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHaifa S. Al-Ruwaili → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Munirah A. Al-Khalidi

Certificate history

16 April 2026

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2026-04-16 13:00

13 April 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-04-13 13:00

10 April 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-04-10 13:00

7 April 2026

  1. Approval: Haifa S. Al-Ruwaili signed “Engineer verifies quantities”

    2026-04-07 13:00

5 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-05 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close