Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 15
- Date
- 2026-05-21
- Hijri
- 4 Dhuʻl-Hijjah 1447 AH
- Reference
- PAY-2024-018-15
Interim payment certificate no. (15)
For the work of May 2026
- Contract number
- SCA/2024/018
- Etimad reference
- 2402270238
- Contract
- Supervision — Qassim qualification centre
- Contractor
- Bait Al-Khebra Engineering Consultants
- Contractor VAT number
- 310101872060003
- Project
- Qassim Vocational Qualification Centre
- Contract period
- 2024-07-01 — 2027-08-31
- Original contract value
- 9,400,000
- Current contract value
- 9,400,000
- Linked milestone
- Supervision to substantial completion · MS-G5 Final handover
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,240,000 |
| 2 | Less: previous certificates | (3,980,000) |
| 3 | Value of work in this certificate | 260,000 |
| 4 | Less: retention (5%) | (13,000) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (13,000) |
| 8 | Net before VAT | 247,000 |
| 9 | Add: value added tax (15%) | 37,050 |
| 10 | Net amount payable to the contractor | 284,050 |
Amount in words: Two hundred eighty-four thousand fifty Saudi riyals only
Retention held up to this certificate: SAR 212K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Resident engineering staff | 5,828,000 | 2,484,000 | 162,000 | 2,646,000 | 45% |
| Visiting specialists | 1,692,000 | 716,000 | 47,000 | 763,000 | 45% |
| Laboratory & testing | 1,128,000 | 429,000 | 29,000 | 458,000 | 41% |
| Reporting & technical office | 752,000 | 351,000 | 22,000 | 373,000 | 50% |
| Total | 9,400,000 | 3,980,000 | 260,000 | 4,240,000 | 45% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Nader F. Al-Asiri
Supervising engineer
Haifa S. Al-Ruwaili
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Munirah A. Al-Khalidi