Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦17⁩ — August 2026

Supervision — Qassim qualification centre

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
17
Date
⁦2026-08-21⁩
Hijri
8 Rabiʻ I 1448 AH
Reference
PAY-2024-018-17

Interim payment certificate no. (⁦17⁩)

For the work of August 2026

Contract number
SCA/2024/018
Etimad reference
2402270238
Contract
Supervision — Qassim qualification centre
Contractor
Bait Al-Khebra Engineering Consultants
Contractor VAT number
310101872060003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-08-31⁩
Original contract value
9,400,000
Current contract value
9,400,000
Linked milestone
Supervision to substantial completion · MS-G5 Final handover

Certificate summary (SAR)

1Total value of work completed to date4,600,000
2Less: previous certificates(4,450,000)
3Value of work in this certificate150,000
4Less: retention (⁦5%⁩)(7,500)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(7,500)
8Net before VAT142,500
9Add: value added tax (15%)21,375
10Net amount payable to the contractor163,875

Amount in words: One hundred sixty-three thousand eight hundred seventy-five Saudi riyals only

Retention held up to this certificate: SAR 230K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff5,828,0002,776,00094,0002,870,000⁦49%⁩
Visiting specialists1,692,000801,00027,000828,000⁦49%⁩
Laboratory & testing1,128,000480,00017,000497,000⁦44%⁩
Reporting & technical office752,000393,00012,000405,000⁦54%⁩
Total9,400,0004,450,000150,0004,600,000⁦49%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Nader F. Al-Asiri

Al-Asiri⁦2026-08-21⁩

Supervising engineer

Haifa S. Al-Ruwaili

Al-Ruwaili⁦2026-08-23⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-08-26⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-08-29⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2026-09-01⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-08-21⁩

    Eng. Nader F. Al-Asiri

  2. Engineer verifies quantities⁦2026-08-23⁩

    Haifa S. Al-Ruwaili · Senior Financial Analyst

    Took 2 days

  3. Project manager certifies⁦2026-08-26⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-08-29⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-01⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision to substantial completionIn progress · ⁦2027-03-11⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHaifa S. Al-Ruwaili → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Munirah A. Al-Khalidi

Certificate history

1 September 2026

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2026-09-01 13:00

29 August 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-08-29 13:00

26 August 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-08-26 13:00

23 August 2026

  1. Approval: Haifa S. Al-Ruwaili signed “Engineer verifies quantities”

    2026-08-23 13:00

21 August 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-08-21 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close