SCA/2024/018
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
50% of the current value paid
Paid
4.7Mof a current value of SAR 9.4M
Value of each certificate
The last 14 — gross and net
Approved: 18
Count: 18 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 18September 2026 | 2026-10-06 | 100K | 5,000 | 0 | 14.3K | 109.3K | Approved | |
| Certificate 17August 2026 | 2026-08-21 | 150K | 7,500 | 0 | 21.4K | 163.9K | Approved | |
| Certificate 16June 2026 | 2026-07-06 | 210K | 10.5K | 0 | 29.9K | 229.4K | Approved | |
| Certificate 15May 2026 | 2026-05-21 | 260K | 13K | 0 | 37.1K | 284.1K | Approved | |
| Certificate 14March 2026 | 2026-04-05 | 250K | 12.5K | 0 | 35.6K | 273.1K | Approved | |
| Certificate 13January 2026 | 2026-02-18 | 330K | 16.5K | 0 | 47K | 360.5K | Approved | |
| Certificate 12December 2025 | 2026-01-03 | 340K | 17K | 0 | 48.5K | 371.5K | Approved | |
| Certificate 11October 2025 | 2025-11-18 | 320K | 16K | 0 | 45.6K | 349.6K | Approved | |
| Certificate 10September 2025 | 2025-10-03 | 390K | 19.5K | 0 | 55.6K | 426.1K | Approved | |
| Certificate 9July 2025 | 2025-08-18 | 340K | 17K | 0 | 48.5K | 371.5K | Approved | |
| Certificate 8June 2025 | 2025-07-03 | 330K | 16.5K | 0 | 47K | 360.5K | Approved | |
| Certificate 7April 2025 | 2025-05-18 | 370K | 18.5K | 0 | 52.7K | 404.2K | Approved | |
| Certificate 6March 2025 | 2025-04-02 | 280K | 14K | 0 | 39.9K | 305.9K | Approved | |
| Certificate 5January 2025 | 2025-02-15 | 290K | 14.5K | 0 | 41.3K | 316.8K | Approved | |
| Certificate 4December 2024 | 2024-12-31 | 260K | 13K | 0 | 37.1K | 284.1K | Approved | |
| Certificate 3October 2024 | 2024-11-15 | 190K | 9,500 | 0 | 27.1K | 207.6K | Approved | |
| Certificate 2September 2024 | 2024-09-30 | 170K | 8,500 | 0 | 24.2K | 185.7K | Approved | |
| Certificate 1July 2024 | 2024-08-15 | 120K | 6,000 | 0 | 17.1K | 131.1K | Approved |