Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2025-09-12
- Hijri
- 20 Rabiʻ I 1447 AH
- Reference
- PAY-2025-002-05
Interim payment certificate no. (5)
For the work of August 2025
- Contract number
- SCA/2025/002
- Etimad reference
- 2503250420
- Contract
- Supply & install smart test-hall proctoring, access control and the monitoring room
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Smart Test-hall Proctoring & Access Control
- Contract period
- 2025-03-02 — 2026-10-31
- Original contract value
- 61,500,000
- Current contract value
- 61,500,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 16,350,000 |
| 2 | Less: previous certificates | (11,730,000) |
| 3 | Value of work in this certificate | 4,620,000 |
| 4 | Less: retention (10%) | (462,000) |
| 5 | Less: advance payment recovery (10%) | (462,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (924,000) |
| 8 | Net before VAT | 3,696,000 |
| 9 | Add: value added tax (15%) | 554,400 |
| 10 | Net amount payable to the contractor | 4,250,400 |
Amount in words: Four million two hundred fifty thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 1.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 4,305,000 | 1,952,000 | 688,000 | 2,640,000 | 61% |
| Earthworks & foundations | 11,070,000 | 3,022,000 | 1,098,000 | 4,120,000 | 37% |
| Concrete & structural works | 19,065,000 | 3,993,000 | 1,582,000 | 5,575,000 | 29% |
| Mechanical, electrical & plumbing | 14,760,000 | 1,904,000 | 843,000 | 2,747,000 | 19% |
| Finishes & external works | 9,225,000 | 749,000 | 355,000 | 1,104,000 | 12% |
| Testing & commissioning | 3,075,000 | 110,000 | 54,000 | 164,000 | 5% |
| Total | 61,500,000 | 11,730,000 | 4,620,000 | 16,350,000 | 27% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani