SCA/2025/002
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
82% of the current value paid
Paid
50.2Mof a current value of SAR 61.5M
Value of each certificate
The last 14 — gross and net
Approved: 14
Count: 14 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 14July 2026 | 2026-08-09 | 3.3M | 330K | 330K | 396K | 3M | Approved | |
| Certificate 13June 2026 | 2026-07-08 | 1.7M | 174K | 174K | 208.8K | 1.6M | Approved | |
| Certificate 12May 2026 | 2026-06-01 | 2.6M | 260K | 260K | 312K | 2.4M | Approved | |
| Certificate 11April 2026 | 2026-04-24 | 3.1M | 309K | 309K | 370.8K | 2.8M | Approved | |
| Certificate 10February 2026 | 2026-03-18 | 4.4M | 440K | 440K | 528K | 4M | Approved | |
| Certificate 9January 2026 | 2026-02-09 | 4.3M | 430K | 430K | 516K | 4M | Approved | |
| Certificate 8December 2025 | 2026-01-02 | 4.6M | 462K | 462K | 554.4K | 4.3M | Approved | |
| Certificate 7November 2025 | 2025-11-26 | 5.4M | 544K | 544K | 652.8K | 5M | Approved | |
| Certificate 6September 2025 | 2025-10-20 | 4.4M | 436K | 436K | 523.2K | 4M | Approved | |
| Certificate 5August 2025 | 2025-09-12 | 4.6M | 462K | 462K | 554.4K | 4.3M | Approved | |
| Certificate 4July 2025 | 2025-08-06 | 4.3M | 425K | 425K | 510K | 3.9M | Approved | |
| Certificate 3June 2025 | 2025-06-30 | 3M | 304K | 304K | 364.8K | 2.8M | Approved | |
| Certificate 2May 2025 | 2025-05-23 | 2.7M | 272K | 272K | 326.4K | 2.5M | Approved | |
| Certificate 1March 2025 | 2025-04-16 | 1.7M | 172K | 172K | 206.4K | 1.6M | Approved |