Certificate ⁦8⁩ — December 2025

Supply & install smart test-hall proctoring, access control and the monitoring room

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
8
Date
⁦2026-01-02⁩
Hijri
13 Rajab 1447 AH
Reference
PAY-2025-002-08

Interim payment certificate no. (⁦8⁩)

For the work of December 2025

Contract number
SCA/2025/002
Etimad reference
2503250420
Contract
Supply & install smart test-hall proctoring, access control and the monitoring room
Contractor
Smart Link Telecom & Security Systems Co.
Contractor VAT number
340303165720003
Project
Smart Test-hall Proctoring & Access Control
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
61,500,000
Current contract value
61,500,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date30,770,000
2Less: previous certificates(26,150,000)
3Value of work in this certificate4,620,000
4Less: retention (⁦10%⁩)(462,000)
5Less: advance payment recovery (⁦10%⁩)(462,000)
6Less: delay and breach penalties0
7Total deductions(924,000)
8Net before VAT3,696,000
9Add: value added tax (15%)554,400
10Net amount payable to the contractor4,250,400

Amount in words: Four million two hundred fifty thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 3.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation4,305,0003,777,000528,0004,305,000⁦100%⁩
Earthworks & foundations11,070,0007,325,0001,093,0008,418,000⁦76%⁩
Concrete & structural works19,065,0008,904,0001,589,00010,493,000⁦55%⁩
Mechanical, electrical & plumbing14,760,0004,237,000932,0005,169,000⁦35%⁩
Finishes & external works9,225,0001,665,000412,0002,077,000⁦23%⁩
Testing & commissioning3,075,000242,00066,000308,000⁦10%⁩
Total61,500,00026,150,0004,620,00030,770,000⁦50%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Ammar Y. Bakhashab

Bakhashab⁦2026-01-02⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-01-04⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-01-07⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-01-10⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-01-13⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-02⁩

    Eng. Ammar Y. Bakhashab

  2. Engineer verifies quantities⁦2026-01-04⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-01-07⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2026-01-10⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-13⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-01-30⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-06-21⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

13 January 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-01-13 13:00

10 January 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-01-10 13:00

7 January 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-01-07 13:00

4 January 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-01-04 13:00

2 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-02 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close