Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 9
- Date
- 2026-02-09
- Hijri
- 21 Shaʻban 1447 AH
- Reference
- PAY-2025-002-09
Interim payment certificate no. (9)
For the work of January 2026
- Contract number
- SCA/2025/002
- Etimad reference
- 2503250420
- Contract
- Supply & install smart test-hall proctoring, access control and the monitoring room
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Smart Test-hall Proctoring & Access Control
- Contract period
- 2025-03-02 — 2026-10-31
- Original contract value
- 61,500,000
- Current contract value
- 61,500,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 35,070,000 |
| 2 | Less: previous certificates | (30,770,000) |
| 3 | Value of work in this certificate | 4,300,000 |
| 4 | Less: retention (10%) | (430,000) |
| 5 | Less: advance payment recovery (10%) | (430,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (860,000) |
| 8 | Net before VAT | 3,440,000 |
| 9 | Add: value added tax (15%) | 516,000 |
| 10 | Net amount payable to the contractor | 3,956,000 |
Amount in words: Three million nine hundred fifty-six thousand Saudi riyals only
Retention held up to this certificate: SAR 3.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 4,305,000 | 3,897,000 | 408,000 | 4,305,000 | 100% |
| Earthworks & foundations | 11,070,000 | 9,156,000 | 1,040,000 | 10,196,000 | 92% |
| Concrete & structural works | 19,065,000 | 10,479,000 | 1,480,000 | 11,959,000 | 63% |
| Mechanical, electrical & plumbing | 14,760,000 | 4,992,000 | 900,000 | 5,892,000 | 40% |
| Finishes & external works | 9,225,000 | 1,962,000 | 405,000 | 2,367,000 | 26% |
| Testing & commissioning | 3,075,000 | 284,000 | 67,000 | 351,000 | 11% |
| Total | 61,500,000 | 30,770,000 | 4,300,000 | 35,070,000 | 57% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani