Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 10
- Date
- 2026-03-18
- Hijri
- 29 Ramadan 1447 AH
- Reference
- PAY-2025-002-10
Interim payment certificate no. (10)
For the work of February 2026
- Contract number
- SCA/2025/002
- Etimad reference
- 2503250420
- Contract
- Supply & install smart test-hall proctoring, access control and the monitoring room
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Smart Test-hall Proctoring & Access Control
- Contract period
- 2025-03-02 — 2026-10-31
- Original contract value
- 61,500,000
- Current contract value
- 61,500,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 39,470,000 |
| 2 | Less: previous certificates | (35,070,000) |
| 3 | Value of work in this certificate | 4,400,000 |
| 4 | Less: retention (10%) | (440,000) |
| 5 | Less: advance payment recovery (10%) | (440,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (880,000) |
| 8 | Net before VAT | 3,520,000 |
| 9 | Add: value added tax (15%) | 528,000 |
| 10 | Net amount payable to the contractor | 4,048,000 |
Amount in words: Four million forty-eight thousand Saudi riyals only
Retention held up to this certificate: SAR 3.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 4,305,000 | 3,961,000 | 344,000 | 4,305,000 | 100% |
| Earthworks & foundations | 11,070,000 | 10,096,000 | 974,000 | 11,070,000 | 100% |
| Concrete & structural works | 19,065,000 | 12,790,000 | 1,615,000 | 14,405,000 | 76% |
| Mechanical, electrical & plumbing | 14,760,000 | 5,674,000 | 957,000 | 6,631,000 | 45% |
| Finishes & external works | 9,225,000 | 2,226,000 | 438,000 | 2,664,000 | 29% |
| Testing & commissioning | 3,075,000 | 323,000 | 72,000 | 395,000 | 13% |
| Total | 61,500,000 | 35,070,000 | 4,400,000 | 39,470,000 | 64% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani