Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 7
- Date
- 2025-11-26
- Hijri
- 5 Jumada II 1447 AH
- Reference
- PAY-2025-002-07
Interim payment certificate no. (7)
For the work of November 2025
- Contract number
- SCA/2025/002
- Etimad reference
- 2503250420
- Contract
- Supply & install smart test-hall proctoring, access control and the monitoring room
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Smart Test-hall Proctoring & Access Control
- Contract period
- 2025-03-02 — 2026-10-31
- Original contract value
- 61,500,000
- Current contract value
- 61,500,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 26,150,000 |
| 2 | Less: previous certificates | (20,710,000) |
| 3 | Value of work in this certificate | 5,440,000 |
| 4 | Less: retention (10%) | (544,000) |
| 5 | Less: advance payment recovery (10%) | (544,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,088,000) |
| 8 | Net before VAT | 4,352,000 |
| 9 | Add: value added tax (15%) | 652,800 |
| 10 | Net amount payable to the contractor | 5,004,800 |
Amount in words: Five million four thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 2.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 4,305,000 | 3,471,000 | 752,000 | 4,223,000 | 98% |
| Earthworks & foundations | 11,070,000 | 5,364,000 | 1,226,000 | 6,590,000 | 60% |
| Concrete & structural works | 19,065,000 | 7,048,000 | 1,869,000 | 8,917,000 | 47% |
| Mechanical, electrical & plumbing | 14,760,000 | 3,334,000 | 1,059,000 | 4,393,000 | 30% |
| Finishes & external works | 9,225,000 | 1,305,000 | 460,000 | 1,765,000 | 19% |
| Testing & commissioning | 3,075,000 | 188,000 | 74,000 | 262,000 | 9% |
| Total | 61,500,000 | 20,710,000 | 5,440,000 | 26,150,000 | 43% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani