Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-06-30
- Hijri
- 5 Muharram 1447 AH
- Reference
- PAY-2025-002-03
Interim payment certificate no. (3)
For the work of June 2025
- Contract number
- SCA/2025/002
- Etimad reference
- 2503250420
- Contract
- Supply & install smart test-hall proctoring, access control and the monitoring room
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Smart Test-hall Proctoring & Access Control
- Contract period
- 2025-03-02 — 2026-10-31
- Original contract value
- 61,500,000
- Current contract value
- 61,500,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 7,480,000 |
| 2 | Less: previous certificates | (4,440,000) |
| 3 | Value of work in this certificate | 3,040,000 |
| 4 | Less: retention (10%) | (304,000) |
| 5 | Less: advance payment recovery (10%) | (304,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (608,000) |
| 8 | Net before VAT | 2,432,000 |
| 9 | Add: value added tax (15%) | 364,800 |
| 10 | Net amount payable to the contractor | 2,796,800 |
Amount in words: Two million seven hundred ninety-six thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 748K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 4,305,000 | 732,000 | 475,000 | 1,207,000 | 28% |
| Earthworks & foundations | 11,070,000 | 1,137,000 | 748,000 | 1,885,000 | 17% |
| Concrete & structural works | 19,065,000 | 1,513,000 | 1,038,000 | 2,551,000 | 13% |
| Mechanical, electrical & plumbing | 14,760,000 | 728,000 | 529,000 | 1,257,000 | 9% |
| Finishes & external works | 9,225,000 | 288,000 | 217,000 | 505,000 | 5% |
| Testing & commissioning | 3,075,000 | 42,000 | 33,000 | 75,000 | 2% |
| Total | 61,500,000 | 4,440,000 | 3,040,000 | 7,480,000 | 12% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani