Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2026-06-30
- Hijri
- 15 Muharram 1448 AH
- Reference
- PAY-2025-024-05
Interim payment certificate no. (5)
For the work of June 2026
- Contract number
- SCA/2025/024
- Etimad reference
- 2504790706
- Contract
- Al-Jouf training centre — rehabilitation works
- Contractor
- Northern Build Contracting Co.
- Contractor VAT number
- 333500279140003
- Project
- Al-Jouf Training Centre Rehabilitation
- Contract period
- 2025-11-02 — 2027-09-30
- Original contract value
- 33,000,000
- Current contract value
- 33,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 9,030,000 |
| 2 | Less: previous certificates | (6,910,000) |
| 3 | Value of work in this certificate | 2,120,000 |
| 4 | Less: retention (10%) | (212,000) |
| 5 | Less: advance payment recovery (10%) | (212,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (424,000) |
| 8 | Net before VAT | 1,696,000 |
| 9 | Add: value added tax (15%) | 254,400 |
| 10 | Net amount payable to the contractor | 1,950,400 |
Amount in words: One million nine hundred fifty thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 903K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,310,000 | 1,143,000 | 315,000 | 1,458,000 | 63% |
| Earthworks & foundations | 5,940,000 | 1,773,000 | 503,000 | 2,276,000 | 38% |
| Concrete & structural works | 10,230,000 | 2,353,000 | 726,000 | 3,079,000 | 30% |
| Mechanical, electrical & plumbing | 7,920,000 | 1,129,000 | 388,000 | 1,517,000 | 19% |
| Finishes & external works | 4,950,000 | 446,000 | 164,000 | 610,000 | 12% |
| Testing & commissioning | 1,650,000 | 66,000 | 24,000 | 90,000 | 5% |
| Total | 33,000,000 | 6,910,000 | 2,120,000 | 9,030,000 | 27% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Badr N. Al-Shammari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani