Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 7
- Date
- 2026-10-06
- Hijri
- 25 Rabiʻ II 1448 AH
- Reference
- PAY-2025-024-07
Interim payment certificate no. (7)
For the work of September 2026
- Contract number
- SCA/2025/024
- Etimad reference
- 2504790706
- Contract
- Al-Jouf training centre — rehabilitation works
- Contractor
- Northern Build Contracting Co.
- Contractor VAT number
- 333500279140003
- Project
- Al-Jouf Training Centre Rehabilitation
- Contract period
- 2025-11-02 — 2027-09-30
- Original contract value
- 33,000,000
- Current contract value
- 33,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 11,500,000 |
| 2 | Less: previous certificates | (10,510,000) |
| 3 | Value of work in this certificate | 990,000 |
| 4 | Less: retention (10%) | (99,000) |
| 5 | Less: advance payment recovery (10%) | (99,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (198,000) |
| 8 | Net before VAT | 792,000 |
| 9 | Add: value added tax (15%) | 118,800 |
| 10 | Net amount payable to the contractor | 910,800 |
Amount in words: Nine hundred ten thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 1.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,310,000 | 1,715,000 | 142,000 | 1,857,000 | 80% |
| Earthworks & foundations | 5,940,000 | 2,669,000 | 229,000 | 2,898,000 | 49% |
| Concrete & structural works | 10,230,000 | 3,582,000 | 340,000 | 3,922,000 | 38% |
| Mechanical, electrical & plumbing | 7,920,000 | 1,746,000 | 186,000 | 1,932,000 | 24% |
| Finishes & external works | 4,950,000 | 696,000 | 80,000 | 776,000 | 16% |
| Testing & commissioning | 1,650,000 | 102,000 | 13,000 | 115,000 | 7% |
| Total | 33,000,000 | 10,510,000 | 990,000 | 11,500,000 | 35% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Badr N. Al-Shammari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Munirah A. Al-Khalidi