Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-08-18
- Hijri
- 5 Rabiʻ I 1448 AH
- Reference
- PAY-2025-024-06
Interim payment certificate no. (6)
For the work of July 2026
- Contract number
- SCA/2025/024
- Etimad reference
- 2504790706
- Contract
- Al-Jouf training centre — rehabilitation works
- Contractor
- Northern Build Contracting Co.
- Contractor VAT number
- 333500279140003
- Project
- Al-Jouf Training Centre Rehabilitation
- Contract period
- 2025-11-02 — 2027-09-30
- Original contract value
- 33,000,000
- Current contract value
- 33,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 10,510,000 |
| 2 | Less: previous certificates | (9,030,000) |
| 3 | Value of work in this certificate | 1,480,000 |
| 4 | Less: retention (10%) | (148,000) |
| 5 | Less: advance payment recovery (10%) | (148,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (296,000) |
| 8 | Net before VAT | 1,184,000 |
| 9 | Add: value added tax (15%) | 177,600 |
| 10 | Net amount payable to the contractor | 1,361,600 |
Amount in words: One million three hundred sixty-one thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 1.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,310,000 | 1,481,000 | 216,000 | 1,697,000 | 73% |
| Earthworks & foundations | 5,940,000 | 2,303,000 | 346,000 | 2,649,000 | 45% |
| Concrete & structural works | 10,230,000 | 3,077,000 | 507,000 | 3,584,000 | 35% |
| Mechanical, electrical & plumbing | 7,920,000 | 1,491,000 | 275,000 | 1,766,000 | 22% |
| Finishes & external works | 4,950,000 | 592,000 | 117,000 | 709,000 | 14% |
| Testing & commissioning | 1,650,000 | 86,000 | 19,000 | 105,000 | 6% |
| Total | 33,000,000 | 9,030,000 | 1,480,000 | 10,510,000 | 32% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Badr N. Al-Shammari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani