Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2026-02-04
- Hijri
- 16 Shaʻban 1447 AH
- Reference
- PAY-2025-024-02
Interim payment certificate no. (2)
For the work of January 2026
- Contract number
- SCA/2025/024
- Etimad reference
- 2504790706
- Contract
- Al-Jouf training centre — rehabilitation works
- Contractor
- Northern Build Contracting Co.
- Contractor VAT number
- 333500279140003
- Project
- Al-Jouf Training Centre Rehabilitation
- Contract period
- 2025-11-02 — 2027-09-30
- Original contract value
- 33,000,000
- Current contract value
- 33,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,680,000 |
| 2 | Less: previous certificates | (950,000) |
| 3 | Value of work in this certificate | 1,730,000 |
| 4 | Less: retention (10%) | (173,000) |
| 5 | Less: advance payment recovery (10%) | (173,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (346,000) |
| 8 | Net before VAT | 1,384,000 |
| 9 | Add: value added tax (15%) | 207,600 |
| 10 | Net amount payable to the contractor | 1,591,600 |
Amount in words: One million five hundred ninety-one thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 268K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,310,000 | 159,000 | 274,000 | 433,000 | 19% |
| Earthworks & foundations | 5,940,000 | 246,000 | 429,000 | 675,000 | 11% |
| Concrete & structural works | 10,230,000 | 323,000 | 591,000 | 914,000 | 9% |
| Mechanical, electrical & plumbing | 7,920,000 | 153,000 | 297,000 | 450,000 | 6% |
| Finishes & external works | 4,950,000 | 60,000 | 121,000 | 181,000 | 4% |
| Testing & commissioning | 1,650,000 | 9,000 | 18,000 | 27,000 | 2% |
| Total | 33,000,000 | 950,000 | 1,730,000 | 2,680,000 | 8% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Badr N. Al-Shammari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani