DMD-2026-017

Indoor air-quality and energy monitoring in SCA buildings

Committee reviewRegulatory requirement
Electronic formPriority evaluation
Priority score
73

Score confirmed by the evaluation panel

Estimated cost
SAR 11.2M
Net present value
SAR 1.5M
Internal rate of return
⁦10.9%⁩
Payback period
⁦3.9⁩ years
Rank in the 2027 plan
#4

of ⁦9⁩ candidates

  1. Gate into «Submitted»DecisionGoDate29 July 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate19 August 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate8 September 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionGoDate29 September 2026FeasibilityComplete
  5. Gate into «Committee review»DecisionGoDate19 October 2026EvaluationComplete
  6. Gate into «Approved»DecisionNot held yetCommittee reviewCurrent stageCurrent stage
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
The Saudi Energy Efficiency Center requires continuous energy monitoring in buildings by the end of 2027, and the authority has received complaints about crowded, poorly ventilated training halls.
Current state
Only two monitoring units cover 15% of the target buildings, with monthly readings.
Objective
A network of 24 automatic monitoring points in training and test halls and reception areas streaming readings live to one platform linked to the Unified Operations Centre.
Expected scope
24 monitoring points, an energy and indoor-environment data platform, a dashboard for branch and centre managers, and three years of operation.

Expected benefits

Compliance

Meets the regulatory requirement before the deadline

Sustainability

An alert within the hour when hall air quality drops

Strategic link

The objectives it serves and how well it aligns

Strategic alignment · Excellent

Related lessons learned

From similar past projects — read them before evaluation

Grid-connection approvals take 4–6 months

From Solar Power for SCA Buildings & Centres

The Saudi Electricity Company took five months to approve connecting the first 12 buildings and centres.

Recommendation: Put the grid operator’s approval on the critical path of any renewable-energy request.