Muqawil Release 4 — project charter
Muqawil Platform — Release 4
1. Purpose
Bring the Authority’s e-services for contractors into Muqawil as one journey — from registration, membership and renewal to certificates, qualification programmes, model contracts and project registration — connected to the national platforms, the commercial register, Balady and Etimad, cutting the time to issue a membership and the cost of every transaction — delivering the strategic objective «simplify regulatory relationships and make doing business easier».
2. Objectives
- Bring 68 contractor e-services into Muqawil with a single journey
- Cut the average time to issue or renew a membership from 21 days to 5
- Lift contractor satisfaction with digital services to 88%
- Reduce cost per transaction by 60%
3. Scope
- A unified Muqawil portal compliant with Digital Government Authority standards, including the membership-fee calculator
- Single sign-on through Nafath; notifying defendant agencies and receiving their replies through the Government Service Bus
- A configurable, no-code request workflow and forms engine
- Migration of memberships, open requests and contractor data from legacy systems
- Change management and training for 420 SCA and service-centre staff
Out of scope
- The mobile app (separate project PRJ-2026-015)
- Re-engineering procedures that would need changes to the Authority’s statute or its bylaws
- The Administrative Execution Platform (a separate project)
4. Success criteria
- 68 e-services live on the platform at close
- 99.9% availability in the first six months
- Penetration test passed with no critical or high findings
- 70% of walk-in requests at HQ and the branches moved online within 12 months
5. Assumptions & constraints
- Nafath and Government Service Bus test environments available as agreed
- Service-owning departments sign off requirements within 10 working days
- The vendor’s named team stays for the whole build
- Approved budget SAR 86.4M including VAT
- Hosting on the government cloud inside the Kingdom only
- Compliance with the ECC and the Personal Data Protection Law
6. Governance & budget
- Sponsor
- Eng. Majed S. Al-Rasheed
- Project manager
- Eng. Sultan F. Al-Ghamdi
- Approved budget
- SAR 86.4M
- Duration
- 2025-02-01 to 2027-03-31
- Overseeing committee
- Projects Steering Committee
The initiation gate approved the charter with two conditions: a full-time project manager within two weeks, and written commitment from the service-owning departments to sign off requirements within ten working days.
Project manager
PMO director