PRJ-2026-001 · From item 2
SCA ERP SystemPlanned to date 74%
- SPI
- 0.82
- Forecast finish
- 2027-02-27
- Budget
- SAR 64.5M
58 days lateMaterial risks: 1Open impediments: 2Corrective plan CP-2026-05
October gate reviews.
Held on
14 October 202611:00 – 12:35
80 of 90 min
Approve the previous minutes
ApprovalDr. Noura M. Al-Otaibi
5 min
SCA ERP planning gate
DecisionDana S. Al-Saleh
45 min
Earlier gate conditions — follow-up
For informationTariq S. Al-Yami
30 min
Approved and locked
1. Approve the previous minutes
Approved.
2. SCA ERP planning gate
PRJ-2026-001Sent back: the schedule ignores the Etimad integration delay.
3. Earlier gate conditions — follow-up
7 of 9 conditions met.
Voting rule: Simple majority; the chair holds the casting vote
SCA ERP project plan sent back for rework
DEC-2026-038Rework
For 5Against 1Abstain 1Carried
Dana Al-Saleh, as the project’s owner, objected and asked for two weeks.
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Quorum: Four of eight members, including the chair or vice-chair
At least 4 voting members needed
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-001 · From item 2
SCA ERP SystemPlanned to date 74%
58 days lateMaterial risks: 1Open impediments: 2Corrective plan CP-2026-05
Agenda item needing a decision · PRJ-2026-001
SCA ERP planning gateFrom item 2
Change request awaiting decision · CR-2026-008
Increase the customisation & integration budgetSCA ERP System
CP-2026-05 · SCA ERP System
FundingSAR 6.8M· Asked from: Executive Committee
More customisation & integration budget through change request CR-2026-008
Nothing