Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2025-03-07
- Hijri
- 7 Ramadan 1446 AH
- Reference
- PAY-2024-012-06
Interim payment certificate no. (6)
For the work of February 2025
- Contract number
- SCA/2024/012
- Etimad reference
- 2401850160
- Contract
- HR self-service implementation
- Contractor
- Integrated Business Systems Co.
- Contractor VAT number
- 310104366820003
- Project
- HR Self-Service
- Contract period
- 2024-06-02 — 2025-09-30
- Original contract value
- 8,800,000
- Current contract value
- 8,800,000
- Linked milestone
- Integration & UAT · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,880,000 |
| 2 | Less: previous certificates | (3,890,000) |
| 3 | Value of work in this certificate | 990,000 |
| 4 | Less: retention (5%) | (49,500) |
| 5 | Less: advance payment recovery (10%) | (99,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (148,500) |
| 8 | Net before VAT | 841,500 |
| 9 | Add: value added tax (15%) | 126,225 |
| 10 | Net amount payable to the contractor | 967,725 |
Amount in words: Nine hundred sixty-seven thousand seven hundred twenty-five Saudi riyals only
Retention held up to this certificate: SAR 244K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 1,320,000 | 903,000 | 170,000 | 1,073,000 | 81% |
| Licences & platform | 1,760,000 | 1,038,000 | 231,000 | 1,269,000 | 72% |
| Build & configuration | 2,640,000 | 1,148,000 | 316,000 | 1,464,000 | 55% |
| Systems integration | 1,320,000 | 446,000 | 140,000 | 586,000 | 44% |
| Testing & acceptance | 880,000 | 216,000 | 77,000 | 293,000 | 33% |
| Training & run | 880,000 | 139,000 | 56,000 | 195,000 | 22% |
| Total | 8,800,000 | 3,890,000 | 990,000 | 4,880,000 | 55% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Mona F. Al-Harbi
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Dana S. Al-Saleh
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Munirah A. Al-Khalidi