Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2026-03-11
- Hijri
- 22 Ramadan 1447 AH
- Reference
- PAY-2025-020-05
Interim payment certificate no. (5)
For the work of February 2026
- Contract number
- SCA/2025/020
- Etimad reference
- 2504510654
- Contract
- Secure enterprise network roll-out
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Secure Enterprise Network
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 108,000,000
- Current contract value
- 108,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 36,920,000 |
| 2 | Less: previous certificates | (27,510,000) |
| 3 | Value of work in this certificate | 9,410,000 |
| 4 | Less: retention (10%) | (941,000) |
| 5 | Less: advance payment recovery (10%) | (941,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,882,000) |
| 8 | Net before VAT | 7,528,000 |
| 9 | Add: value added tax (15%) | 1,129,200 |
| 10 | Net amount payable to the contractor | 8,657,200 |
Amount in words: Eight million six hundred fifty-seven thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 3.7M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 7,560,000 | 4,605,000 | 1,357,000 | 5,962,000 | 79% |
| Earthworks & foundations | 19,440,000 | 7,119,000 | 2,185,000 | 9,304,000 | 48% |
| Concrete & structural works | 33,480,000 | 9,363,000 | 3,227,000 | 12,590,000 | 38% |
| Mechanical, electrical & plumbing | 25,920,000 | 4,435,000 | 1,768,000 | 6,203,000 | 24% |
| Finishes & external works | 16,200,000 | 1,737,000 | 755,000 | 2,492,000 | 15% |
| Testing & commissioning | 5,400,000 | 251,000 | 118,000 | 369,000 | 7% |
| Total | 108,000,000 | 27,510,000 | 9,410,000 | 36,920,000 | 34% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani