Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 9
- Date
- 2026-10-07
- Hijri
- 26 Rabiʻ II 1448 AH
- Reference
- PAY-2026-016
Interim payment certificate no. (9)
For the work of September 2026
- Contract number
- SCA/2025/020
- Etimad reference
- 2504510654
- Contract
- Secure enterprise network roll-out
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Secure Enterprise Network
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 108,000,000
- Current contract value
- 108,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 59,400,000 |
| 2 | Less: previous certificates | (54,800,000) |
| 3 | Value of work in this certificate | 4,600,000 |
| 4 | Less: retention (10%) | (460,000) |
| 5 | Less: advance payment recovery (10%) | (460,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (920,000) |
| 8 | Net before VAT | 3,680,000 |
| 9 | Add: value added tax (15%) | 552,000 |
| 10 | Net amount payable to the contractor | 4,232,000 |
Amount in words: Four million two hundred thirty-two thousand Saudi riyals only
Retention held up to this certificate: SAR 5.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 7,560,000 | 7,100,000 | 460,000 | 7,560,000 | 100% |
| Earthworks & foundations | 19,440,000 | 15,893,000 | 1,109,000 | 17,002,000 | 87% |
| Concrete & structural works | 33,480,000 | 18,672,000 | 1,583,000 | 20,255,000 | 60% |
| Mechanical, electrical & plumbing | 25,920,000 | 9,027,000 | 952,000 | 9,979,000 | 38% |
| Finishes & external works | 16,200,000 | 3,584,000 | 426,000 | 4,010,000 | 25% |
| Testing & commissioning | 5,400,000 | 524,000 | 70,000 | 594,000 | 11% |
| Total | 108,000,000 | 54,800,000 | 4,600,000 | 59,400,000 | 55% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani