SCA/2025/020
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 1.2M — if approved the value becomes SAR 109.2M
55% of the current value paid
Paid
59.4Mof a current value of SAR 108M
Value of each certificate
The last 9 — gross and net
Approved: 9
Count: 9 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 9September 2026 | 2026-10-07 | 4.6M | 460K | 460K | 552K | 4.2M | Approved | |
| Certificate 8August 2026 | 2026-09-05 | 3.7M | 369K | 369K | 442.8K | 3.4M | Approved | |
| Certificate 7June 2026 | 2026-07-08 | 6.8M | 679K | 679K | 814.8K | 6.2M | Approved | |
| Certificate 6April 2026 | 2026-05-09 | 7.4M | 740K | 740K | 888K | 6.8M | Approved | |
| Certificate 5February 2026 | 2026-03-11 | 9.4M | 941K | 941K | 1.1M | 8.7M | Approved | |
| Certificate 4December 2025 | 2026-01-10 | 9.8M | 977K | 977K | 1.2M | 9M | Approved | |
| Certificate 3October 2025 | 2025-11-12 | 7.3M | 730K | 730K | 876K | 6.7M | Approved | |
| Certificate 2August 2025 | 2025-09-13 | 6.7M | 668K | 668K | 801.6K | 6.1M | Approved | |
| Certificate 1June 2025 | 2025-07-16 | 3.8M | 376K | 376K | 451.2K | 3.5M | Approved |