Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-11-12
- Hijri
- 21 Jumada I 1447 AH
- Reference
- PAY-2025-020-03
Interim payment certificate no. (3)
For the work of October 2025
- Contract number
- SCA/2025/020
- Etimad reference
- 2504510654
- Contract
- Secure enterprise network roll-out
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Secure Enterprise Network
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 108,000,000
- Current contract value
- 108,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 17,740,000 |
| 2 | Less: previous certificates | (10,440,000) |
| 3 | Value of work in this certificate | 7,300,000 |
| 4 | Less: retention (10%) | (730,000) |
| 5 | Less: advance payment recovery (10%) | (730,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,460,000) |
| 8 | Net before VAT | 5,840,000 |
| 9 | Add: value added tax (15%) | 876,000 |
| 10 | Net amount payable to the contractor | 6,716,000 |
Amount in words: Six million seven hundred sixteen thousand Saudi riyals only
Retention held up to this certificate: SAR 1.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 7,560,000 | 1,739,000 | 1,128,000 | 2,867,000 | 38% |
| Earthworks & foundations | 19,440,000 | 2,690,000 | 1,780,000 | 4,470,000 | 23% |
| Concrete & structural works | 33,480,000 | 3,554,000 | 2,495,000 | 6,049,000 | 18% |
| Mechanical, electrical & plumbing | 25,920,000 | 1,694,000 | 1,286,000 | 2,980,000 | 11% |
| Finishes & external works | 16,200,000 | 666,000 | 531,000 | 1,197,000 | 7% |
| Testing & commissioning | 5,400,000 | 97,000 | 80,000 | 177,000 | 3% |
| Total | 108,000,000 | 10,440,000 | 7,300,000 | 17,740,000 | 16% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani