Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-09-13
- Hijri
- 21 Rabiʻ I 1447 AH
- Reference
- PAY-2025-020-02
Interim payment certificate no. (2)
For the work of August 2025
- Contract number
- SCA/2025/020
- Etimad reference
- 2504510654
- Contract
- Secure enterprise network roll-out
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Secure Enterprise Network
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 108,000,000
- Current contract value
- 108,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 10,440,000 |
| 2 | Less: previous certificates | (3,760,000) |
| 3 | Value of work in this certificate | 6,680,000 |
| 4 | Less: retention (10%) | (668,000) |
| 5 | Less: advance payment recovery (10%) | (668,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,336,000) |
| 8 | Net before VAT | 5,344,000 |
| 9 | Add: value added tax (15%) | 801,600 |
| 10 | Net amount payable to the contractor | 6,145,600 |
Amount in words: Six million one hundred forty-five thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 7,560,000 | 634,000 | 1,052,000 | 1,686,000 | 22% |
| Earthworks & foundations | 19,440,000 | 978,000 | 1,653,000 | 2,631,000 | 14% |
| Concrete & structural works | 33,480,000 | 1,279,000 | 2,281,000 | 3,560,000 | 11% |
| Mechanical, electrical & plumbing | 25,920,000 | 601,000 | 1,153,000 | 1,754,000 | 7% |
| Finishes & external works | 16,200,000 | 234,000 | 471,000 | 705,000 | 4% |
| Testing & commissioning | 5,400,000 | 34,000 | 70,000 | 104,000 | 2% |
| Total | 108,000,000 | 3,760,000 | 6,680,000 | 10,440,000 | 10% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani