Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 1
- Date
- 2025-07-16
- Hijri
- 21 Muharram 1447 AH
- Reference
- PAY-2025-020-01
Interim payment certificate no. (1)
For the work of June 2025
- Contract number
- SCA/2025/020
- Etimad reference
- 2504510654
- Contract
- Secure enterprise network roll-out
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Secure Enterprise Network
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 108,000,000
- Current contract value
- 108,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 3,760,000 |
| 2 | Less: previous certificates | 0 |
| 3 | Value of work in this certificate | 3,760,000 |
| 4 | Less: retention (10%) | (376,000) |
| 5 | Less: advance payment recovery (10%) | (376,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (752,000) |
| 8 | Net before VAT | 3,008,000 |
| 9 | Add: value added tax (15%) | 451,200 |
| 10 | Net amount payable to the contractor | 3,459,200 |
Amount in words: Three million four hundred fifty-nine thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 376K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 7,560,000 | 0 | 606,000 | 606,000 | 8% |
| Earthworks & foundations | 19,440,000 | 0 | 948,000 | 948,000 | 5% |
| Concrete & structural works | 33,480,000 | 0 | 1,282,000 | 1,282,000 | 4% |
| Mechanical, electrical & plumbing | 25,920,000 | 0 | 632,000 | 632,000 | 2% |
| Finishes & external works | 16,200,000 | 0 | 254,000 | 254,000 | 2% |
| Testing & commissioning | 5,400,000 | 0 | 38,000 | 38,000 | 1% |
| Total | 108,000,000 | 0 | 3,760,000 | 3,760,000 | 3% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani