Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2026-09-05
- Hijri
- 23 Rabiʻ I 1448 AH
- Reference
- PAY-2025-020-08
Interim payment certificate no. (8)
For the work of August 2026
- Contract number
- SCA/2025/020
- Etimad reference
- 2504510654
- Contract
- Secure enterprise network roll-out
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Secure Enterprise Network
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 108,000,000
- Current contract value
- 108,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 54,800,000 |
| 2 | Less: previous certificates | (51,110,000) |
| 3 | Value of work in this certificate | 3,690,000 |
| 4 | Less: retention (10%) | (369,000) |
| 5 | Less: advance payment recovery (10%) | (369,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (738,000) |
| 8 | Net before VAT | 2,952,000 |
| 9 | Add: value added tax (15%) | 442,800 |
| 10 | Net amount payable to the contractor | 3,394,800 |
Amount in words: Three million three hundred ninety-four thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 5.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 7,560,000 | 7,147,000 | 413,000 | 7,560,000 | 100% |
| Earthworks & foundations | 19,440,000 | 14,224,000 | 876,000 | 15,100,000 | 78% |
| Concrete & structural works | 33,480,000 | 17,418,000 | 1,269,000 | 18,687,000 | 56% |
| Mechanical, electrical & plumbing | 25,920,000 | 8,459,000 | 747,000 | 9,206,000 | 36% |
| Finishes & external works | 16,200,000 | 3,368,000 | 331,000 | 3,699,000 | 23% |
| Testing & commissioning | 5,400,000 | 494,000 | 54,000 | 548,000 | 10% |
| Total | 108,000,000 | 51,110,000 | 3,690,000 | 54,800,000 | 51% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani