Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-11-28
- Hijri
- 7 Jumada II 1447 AH
- Reference
- PAY-2025-025-02
Interim payment certificate no. (2)
For the work of November 2025
- Contract number
- SCA/2025/025
- Etimad reference
- 2504860719
- Contract
- Arar vocational qualification centre — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Arar Vocational Qualification Centre
- Contract period
- 2025-08-03 — 2027-08-31
- Original contract value
- 196,000,000
- Current contract value
- 196,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 18,320,000 |
| 2 | Less: previous certificates | (6,390,000) |
| 3 | Value of work in this certificate | 11,930,000 |
| 4 | Less: retention (10%) | (1,193,000) |
| 5 | Less: advance payment recovery (10%) | (1,193,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,386,000) |
| 8 | Net before VAT | 9,544,000 |
| 9 | Add: value added tax (15%) | 1,431,600 |
| 10 | Net amount payable to the contractor | 10,975,600 |
Amount in words: Ten million nine hundred seventy-five thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 1.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 13,720,000 | 1,077,000 | 1,881,000 | 2,958,000 | 22% |
| Earthworks & foundations | 35,280,000 | 1,663,000 | 2,954,000 | 4,617,000 | 13% |
| Concrete & structural works | 60,760,000 | 2,174,000 | 4,073,000 | 6,247,000 | 10% |
| Mechanical, electrical & plumbing | 47,040,000 | 1,021,000 | 2,057,000 | 3,078,000 | 7% |
| Finishes & external works | 29,400,000 | 398,000 | 839,000 | 1,237,000 | 4% |
| Testing & commissioning | 9,800,000 | 57,000 | 126,000 | 183,000 | 2% |
| Total | 196,000,000 | 6,390,000 | 11,930,000 | 18,320,000 | 9% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ibrahim A. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani