Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 4
- Date
- 2026-04-22
- Hijri
- 5 Dhuʻl-Qiʻdah 1447 AH
- Reference
- PAY-2025-025-04
Interim payment certificate no. (4)
For the work of April 2026
- Contract number
- SCA/2025/025
- Etimad reference
- 2504860719
- Contract
- Arar vocational qualification centre — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Arar Vocational Qualification Centre
- Contract period
- 2025-08-03 — 2027-08-31
- Original contract value
- 196,000,000
- Current contract value
- 196,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 45,320,000 |
| 2 | Less: previous certificates | (30,620,000) |
| 3 | Value of work in this certificate | 14,700,000 |
| 4 | Less: retention (10%) | (1,470,000) |
| 5 | Less: advance payment recovery (10%) | (1,470,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,940,000) |
| 8 | Net before VAT | 11,760,000 |
| 9 | Add: value added tax (15%) | 1,764,000 |
| 10 | Net amount payable to the contractor | 13,524,000 |
Amount in words: Thirteen million five hundred twenty-four thousand Saudi riyals only
Retention held up to this certificate: SAR 4.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 13,720,000 | 5,101,000 | 2,218,000 | 7,319,000 | 53% |
| Earthworks & foundations | 35,280,000 | 7,895,000 | 3,526,000 | 11,421,000 | 32% |
| Concrete & structural works | 60,760,000 | 10,424,000 | 5,030,000 | 15,454,000 | 25% |
| Mechanical, electrical & plumbing | 47,040,000 | 4,965,000 | 2,649,000 | 7,614,000 | 16% |
| Finishes & external works | 29,400,000 | 1,952,000 | 1,107,000 | 3,059,000 | 10% |
| Testing & commissioning | 9,800,000 | 283,000 | 170,000 | 453,000 | 5% |
| Total | 196,000,000 | 30,620,000 | 14,700,000 | 45,320,000 | 23% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ibrahim A. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani