Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2026-02-08
- Hijri
- 20 Shaʻban 1447 AH
- Reference
- PAY-2025-025-03
Interim payment certificate no. (3)
For the work of January 2026
- Contract number
- SCA/2025/025
- Etimad reference
- 2504860719
- Contract
- Arar vocational qualification centre — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Arar Vocational Qualification Centre
- Contract period
- 2025-08-03 — 2027-08-31
- Original contract value
- 196,000,000
- Current contract value
- 196,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 30,620,000 |
| 2 | Less: previous certificates | (18,320,000) |
| 3 | Value of work in this certificate | 12,300,000 |
| 4 | Less: retention (10%) | (1,230,000) |
| 5 | Less: advance payment recovery (10%) | (1,230,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,460,000) |
| 8 | Net before VAT | 9,840,000 |
| 9 | Add: value added tax (15%) | 1,476,000 |
| 10 | Net amount payable to the contractor | 11,316,000 |
Amount in words: Eleven million three hundred sixteen thousand Saudi riyals only
Retention held up to this certificate: SAR 3.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 13,720,000 | 3,042,000 | 1,904,000 | 4,946,000 | 36% |
| Earthworks & foundations | 35,280,000 | 4,712,000 | 3,004,000 | 7,716,000 | 22% |
| Concrete & structural works | 60,760,000 | 6,238,000 | 4,203,000 | 10,441,000 | 17% |
| Mechanical, electrical & plumbing | 47,040,000 | 2,982,000 | 2,162,000 | 5,144,000 | 11% |
| Finishes & external works | 29,400,000 | 1,176,000 | 891,000 | 2,067,000 | 7% |
| Testing & commissioning | 9,800,000 | 170,000 | 136,000 | 306,000 | 3% |
| Total | 196,000,000 | 18,320,000 | 12,300,000 | 30,620,000 | 16% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ibrahim A. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani