Certificate ⁦3⁩ — January 2026

Arar vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2026-02-08⁩
Hijri
20 Shaʻban 1447 AH
Reference
PAY-2025-025-03

Interim payment certificate no. (⁦3⁩)

For the work of January 2026

Contract number
SCA/2025/025
Etimad reference
2504860719
Contract
Arar vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Arar Vocational Qualification Centre
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
196,000,000
Current contract value
196,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date30,620,000
2Less: previous certificates(18,320,000)
3Value of work in this certificate12,300,000
4Less: retention (⁦10%⁩)(1,230,000)
5Less: advance payment recovery (⁦10%⁩)(1,230,000)
6Less: delay and breach penalties0
7Total deductions(2,460,000)
8Net before VAT9,840,000
9Add: value added tax (15%)1,476,000
10Net amount payable to the contractor11,316,000

Amount in words: Eleven million three hundred sixteen thousand Saudi riyals only

Retention held up to this certificate: SAR 3.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation13,720,0003,042,0001,904,0004,946,000⁦36%⁩
Earthworks & foundations35,280,0004,712,0003,004,0007,716,000⁦22%⁩
Concrete & structural works60,760,0006,238,0004,203,00010,441,000⁦17%⁩
Mechanical, electrical & plumbing47,040,0002,982,0002,162,0005,144,000⁦11%⁩
Finishes & external works29,400,0001,176,000891,0002,067,000⁦7%⁩
Testing & commissioning9,800,000170,000136,000306,000⁦3%⁩
Total196,000,00018,320,00012,300,00030,620,000⁦16%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-02-08⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-10⁩

Project manager

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-13⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-02-16⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-02-19⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-08⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-02-10⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-02-13⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 3 days

  4. Payment order prepared⁦2026-02-16⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-19⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2026-03-03⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-08-04⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ibrahim A. Al-Ghamdi → Dr. Abdullah S. Al-Qahtani

Certificate history

19 February 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-02-19 13:00

16 February 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-02-16 13:00

13 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Project manager certifies”

    2026-02-13 13:00

10 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-02-10 13:00

8 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close